Grodno Azot continues active modernization of its production capacities. At present, two key investment projects are being implemented at the enterprise, which will significantly strengthen its position in the nitrogen fertilizer market and improve production efficiency.
According to Grodno Azot Director General Igor Lyashenko, the enterprise is finishing the financial year having met the vast majority of all assigned targets. The needs of agriculture have been met, volumes have been supplied by assortment, and the schedule for next year has been agreed.
Yevgeny Gachko, Grodno Azot Deputy Director General, spoke about the investment projects currently being implemented at the enterprise. «The first is the reconstruction of the fourth stage of the ammonia production shop. The estimated cost of the project is around Br324 million. From 2022 to 2026, extensive work was carried out at this facility. The main goal of the project is to increase daily ammonia output and improve the energy efficiency of production. Despite sanctions pressure, we have renewed a quarter of the main process equipment and installed more than ten new units. An important result of this work has been a reduction in the specific consumption rate of natural gas per tonne of ammonia produced. Installing equipment during turnaround periods made it possible to minimize the shop’s downtime for repairs. Thanks to this, we were able to combine the reconstruction with scheduled shutdown repairs. The project required non-standard solutions and the use of universal lifting equipment. In total, 1,700 tonnes of equipment were installed at the facility and more than 10 km of pipelines were laid,» he said.

The project is aimed at increasing ammonia output from 1,620 to 2,100 tonnes per day. The work will be carried out in two stages. The first stage, scheduled for completion in 2026, will increase capacity to 1,750 tonnes per day. The second stage, which envisages reaching full capacity of 2,100 tonnes, is planned for completion by 2030.
The second facility is the construction of ammonium nitrate production with a capacity of 1,500 tonnes per day. This project is included in Belarus’ social and economic development program for the next five years. The cost of the project is around Br546 million, Yevgeny Gachko said.
The project is aimed at producing a new product, ammonium nitrate, which will make it possible to diversify the output of nitrogen fertilizers to meet market needs. «This is a strategic step for the enterprise. The launch of this production will expand the range of products and diversify the output of mineral fertilizers. The construction is now in an active phase. More than 2,000 tonnes of metal structures have already been installed and more than 10,000 cubic meters of concrete poured. The planned completion date for the project is 2028,» Yevgeny Gachko said.
The prime minister spoke with the engineering and technical staff of the Ammonia-4 shop. They discussed wages, housing conditions and working conditions. Social guarantees and personnel issues were also raised.
Discussion of the implementation of investment projects in the petrochemical industry continued at the premises of Grodno Azot. Fertilizer and chemical fiber producers, who among others determine the development strategy for the country’s petrochemical complex, have been invited to the discussion. Participants will exchange accumulated experience and discuss further steps to develop production and improve the competitiveness of their products.
«We will look at the current state and implementation of the industry’s investment projects. Today we learned how they are being implemented at Grodno Azot. A good example. We see the result and where we are heading. But, unfortunately, this is not happening at such a level at all enterprises. Therefore, we will work out what we need to do so that everything we agree on and plan is implemented within the exact established deadlines,» Aleksandr Turchin said.